The Mariana dam disaster was an environmental disaster near Mariana, Minas Gerais, Brazil. On 5 November 2015, the Fundão tailings dam at the Germano iron ore mine of the Samarco Mariana Mining Complex near Mariana, suffered a catastrophic failure, resulting in flooding that devastated the downstream villages of Bento Rodrigues and Paracatu de Baixo (40 km (25 mi) from Bento Rodrigues), killing 19 people.[5][6] The extent of the damage caused by the tailings dam collapse is the largest ever recorded, with pollutants spread along 668 km of watercourses.[7]
The failure of the dam released 43.7 e6m3 of mine tailings into the Doce River, causing a toxic brown mudflow to pollute the river and beaches near the mouth when it reached the Atlantic Ocean 17 days later.[8][9][10][11] The disaster created a humanitarian crisis as hundreds were displaced and cities along the Doce River suffered water shortages when their water supplies were polluted.
The total impact of the disaster, including the reason for failure and the environmental consequences, are officially under investigation and remain unclear.[12] The owner of the Bento Rodrigues dam, Samarco, was subject to extensive litigation and government sanctions. In 2016, charges of manslaughter and environmental damage were filed against 21 executives, including Samarco's former CEO and representatives from Samarco's owners, Vale and BHP Billiton, on its board of directors. Controversy over the disaster grew after a 2013 internal report, which indicated structural issues with the dam, was leaked.[13][14][15][16]
On 6 November 2024, the President of the Brazilian Supreme Federal Court (STF), Luis Roberto Barroso, granted approval to a R$170 billion (approximately US$30 billion) compensation agreement to repair the damages caused by the disaster, signed between the mining companies and the Brazilian government.[17]
On 14 November 2025, the High Court in England ruled that BHP Group was strictly liable for the disaster, citing negligence, technical warnings and lack of essential studies, which permitted the height of the dam to increase beyond safe levels.
Background
The Fundão tailings dam was constructed and owned by Samarco, a mining company, near Mariana, a municipality 67 km southeast of Belo Horizonte, in the state of Minas Gerais, Brazil. The tailings dam was built by Samarco to accommodate the waste resulting from the extraction of iron ore taken from the extensive Germano mine, located in the Mariana district of Santa Rita Durão. The Fundão dam was constructed in hills near the village and subdistrict of Bento Rodrigues, located 14 km north of Mariana city.
Incident
At approximately 3:30 pm on 5 November 2015, the Fundão dam began to leak. Immediately, a team of outsourced employees was sent to the scene, and they tried to mitigate the leak by deflating part of the reservoir. At around 4:20 pm, a rupture occurred, releasing a large volume of toxic sludge into the Santarém river valley. Bento Rodrigues, which lies 2.5 km away in the valley below the dam, was almost entirely flooded by the cascade of toxic water and mud.[18]
The incident rendered Bento Rodrigues completely inaccessible by road, hindering firefighters' rescue efforts. The only available method of transport into or out of the location was via helicopter. There was a school in the area where the flood occurred, and the teachers were able to remove the students before the school was flooded by the toxic sludge.
Other villages and districts in the Gualaxo river valley were also severely affected by the disaster. The midtown area of Barra Longa, a small city located 60 km from Mariana, had residential and commercial buildings flooded by the mud; the district of Gesteira, built on the banks of Gualaxo river, also had houses completely destroyed by the flood; some of the district residents were rescued by helicopter.
Samarco and the neighbouring communities did not have a contingency plan or evacuation routes in the event of dam failure. Had such plans existed, residents may have been able to evacuate in a timely manner to more secure regions. Around 600 people were evacuated to Mariana, and troops of the Brazilian Armed Forces were deployed to assist.[2][4]
Impact
According to a United Nations report, the tailings slurry traveled 620 km downriver, eventually reaching the Atlantic Ocean. Nineteen people were killed, entire fish populations were killed immediately when the slurry buried them or clogged their gills, and the mudflow destroyed 1469 ha of riparian forest.[19]
Contamination of the Doce River
At around 6:30 pm on 5 November, the tailings of iron ore reached the Doce River. The river basin has a drainage area of about 86,700 sqkm, with 86% in Minas Gerais and Espírito Santo. In total, the river covers 230 municipalities that use its bed for subsistence. The waste also reached the hydroelectric power plant of Risoleta Neves in Santa Cruz do Escalvado within 100 kilometres of Mariana. According to the company that runs the power plant, its functioning was not affected.
On 9 November, the city of Governador Valadares stopped the water intakes due to the mud on the Doce River. The next day, a State of Public Calamity was decreed in response to the water shortage in the city. According to analyses carried out in the city, the mud contains greater than acceptable concentrations of heavy metals, substances harmful to health, such as arsenic, lead and mercury.[20]
There are concerns about contamination of the nearby, a tributary of the Doce River, due to the toxic substances stored at the facility.[2]
Contamination of southern Atlantic Ocean
On 22 November, fine waste particles in suspension reached the Atlantic Ocean.[21][22]
On 7 January 2016, fine waste particles reached the southern Bahia littoral zone.[23] Environmentalists are monitoring the impact to the Abrolhos Marine National Park wildlife. The park is considered of vital importance to the Brazilian ecosystem since it hosts the greatest marine biodiversity in the whole southern Atlantic Ocean.[24]
Aftermath
Investigation of the causes
On the first quarter of November 2015, the Brazilian Chamber of Deputies and the state chambers of Minas Gerais and Espírito Santo each created a special commission to investigate the collapse. According to the media reports, many of the deputies that composed such commissions had received donations from Vale to finance their campaigns. Such donations, up to R$2.6 million are legal, and were reported by the then-candidates to the Brazilian Election Justice. However, critics argued that the deputies' participation was clearly biased.[25][26]
In January 2016, leaked internal documents from 14 months before the disaster revealed that Samarco had been warned about the possibility of the dam collapsing.[27] Joaquim Pimenta de Ávila, an engineer who was regarded as one of the foremost tailing dam engineers in Brazil, had been contracted by Samarco between 2008 and 2012 to design and oversee the construction of the Fundão dam.
From 2013, Ávila was hired part-time as a consultant to inspect the dam, and a technical report he wrote from September 2014 lists severe structural problems on the dam (in the form of cracks) and measures to mitigate them, the main one being the construction of a buttress. Ávila originally designed the dam in 2006, and it was erected by construction firm Camter. However, construction defects within the dam led to a design change by Camter that allowed for more saturation.[28] Samarco claimed to have implemented all the recommendations from Ávila, and that the dam was in the process of being heightened when the impoundment reached its maximum holding capacity and began to leak. However, Samarco failed to comment specifically about the buttress, and claims that it was never warned about the severity of the structural damages, nor about the imminence of a catastrophic failure.
In August 2016, the report of an investigation panel constituted by Samarco and its shareholders was published online.[29] The investigation panel findings indicated that the liquefaction flowsliding resulted from multiple factors, including an increase in the saturation of the tailings due to modifications in the design of the dam and the presence of soft slimes in unintended areas on the left abutment of the dam. Another study indicated that the dam failure could not be predicted based on simple limit equilibrium analyses and that only a complex failure mechanism would explain the dam collapse.[30]
Sanctions to Samarco
The Minas Gerais government suspended Samarco's activities immediately after the disaster.[31]
Next, the Brazilian government fined Samarco BRL250 million (US$66.3 million) for the incident.[32][33] The fine was preliminary and was expected to be increased if the two companies were found guilty of water pollution and damages.
Succumbing to external pressure, BHP Billiton, together with Vale and Samarco, signed in 2016 an agreement with the Brazilian federal and state authorities. In January 2016, the Brazilian government and Samarco reached an agreement and a fine of BRL20 billion (US$4.8 billion) was issued.[34] The penalty did not include compensation to people affected by the disaster, and the cost of recovering the polluted area. By July 2016, BHP made a provision of US$2.3-2.5 billion for costs associated with the compensation agreement between Samarco's shareholders (BHP and Vale) and Brazilian federal, state and municipal authorities.[35]
Legal consequences
Vale and BHP Billiton own Samarco as a joint venture, with each company possessing a 50% stake.[36] As of 2018, the companies remain in negotiations with Brazilian authorities in efforts to settle out of court.
In March 2016, Samarco agreed to pay US$2.3 billion in compensation. Australia's ABC reported that Samarco and its joint venture partners would "establish a foundation to develop and execute environmental and socio-economic programs to restore the environment, local communities and social conditions of the affected areas."[37]
In June 2016, an AUD$8 billion civil suit which was reinstated by Brazil's Superior Court after the original agreement was suspended. BHP, along with its Samarco joint venture partner Vale, face a separate $55 billion suit lodged by federal prosecutors.[35]
In October 2016 it was reported that Brazilian prosecutors had filed manslaughter and environmental charges against 21 people[38] including top executives of Samarco's Parent Companies: BHP Billiton, an Anglo-Australian multinational mining, metals and petroleum company headquartered in Melbourne, Australia and the world's largest mining company, and Vale, the third-largest mining company in the world and the Public Eye People's Worst Company award winner of 2012.[4][39]
In June 2018, Samarco, Vale and BHP signed an agreement to drop a US$7 billion lawsuit and allow two years for the companies to address the greater US$55 billion suit seeking social, environmental and economic compensation.[40]
Class action lawsuits
In August 2018, BHP settled a class action suit in the US for US$50 million, with no admission of liability.[41] At the same time, it was facing a class action lawsuit from shareholders in Australia related to the dam failure[42] and losses incurred by shareholders following company disclosures to the market regarding the safety of the dam. The class action is expected to be one of the largest in Australian history, with 30,000 BHP shareholders involved, with a combined shareholding of 330 million shares, valued at over AU$10 billion (at 30 October 2018).[43]
In November 2018, UK-based legal firm SPG Law, now Pogust Goodhead, filed a US$5 billion group action in the High Court of Justice at Liverpool under Brazilian law against BHP Billiton on behalf of 235,000 Brazilian individuals and organisations, including municipal governments, utility companies, indigenous tribes and the Catholic Church.[44] The lawsuit is one of the biggest legal claims ever filed in a British court.[45] The case, which has been the subject of jurisdictional challenge, was delayed due to the COVID-19 pandemic.[46]
In November 2020, in the High Court sitting in Manchester, the claims were struck out on the grounds that they amounted to an abuse of the process of the court.[47] On 27 July 2021, the Court of Appeal granted the claimants leave to appeal against the November 2020 ruling.[48][49] In July 2022, the Court of Appeal allowed the appeal opening the way for the case to proceed in the English courts.[50][51] In 2023, it was announced that Pogust Goodhead had secured a £450m investment from US-based firm Gramercy Funds Management to help fund the Mariana case and "resolve existing cases successfully".[52]
In March 2023, it was reported that BHP faces an enlarged class-action lawsuit seeking damages of up to U$65 billion for its role in the dam collapse, with the number of claimants more than tripling to 700,000.[53] Approximately 100,000 claimants subsequently exited the claim.[54] Of the remaining 600,000 claimants, 200,000 had already received a total of US$2 billion in compensation through Brazilian proceedings.[55] In April 2024, it was reported that payouts from the court action were to be delayed past the original claimant forecasts, with the case now expected to be completed in 2027.[56] During the trial, it emerged that claims had been filed for oily hair, chickenpox, Alzheimer's disease, and flowers not being as beautiful as before.[57] Lawyers fees in the case are projected to exceed US$680 million.[58] BHP continues to deny the claim in its entirety.[59] In August 2025, BHP Group and Vale had offered US$1.4 billion to settle the case.[60]
On 14 November 2025, High Court judge Finola O'Farrell ruled BHP strictly liable for the disaster. O'Farrell affirmed that "the risk of collapse of the dam was foreseeable", adding: "It is inconceivable that a decision would have been taken to continue raising the height of the dam in those circumstances and the collapse could have been averted".[61] Furthermore, the judge cited serious negligence, as technical warnings were ignored and essential studies were not conducted, allowing the dam to continue being raised even in the face of clear signs of risk. The group stated it intends to appeal over the decision. The amount of compensation to be paid will be determined in another trial, scheduled for October 2026.[62][63] Amid the 2025 United Nations Climate Change Conference held in the Brazilian city of Belém, the Movimento dos Atingidos por Barragens (Movement of People Affected by Dams—MAB) celebrated the decision: "It actually legitimises the struggle. And the fact that the Court finds BHP liable shows that they really have to pay and have to make reparations to those affected."[64]
Class action lawsuits
In August 2018, BHP settled a class action suit in the US for US$50 million, with no admission of liability.[41] At the same time, it was facing a class action lawsuit from shareholders in Australia related to the dam failure[42] and losses incurred by shareholders following company disclosures to the market regarding the safety of the dam. The class action is expected to be one of the largest in Australian history, with 30,000 BHP shareholders involved, with a combined shareholding of 330 million shares, valued at over AU$10 billion (at 30 October 2018).[43]
In November 2018, UK-based legal firm SPG Law, now Pogust Goodhead, filed a US$5 billion group action in the High Court of Justice at Liverpool under Brazilian law against BHP Billiton on behalf of 235,000 Brazilian individuals and organisations, including municipal governments, utility companies, indigenous tribes and the Catholic Church.[44] The lawsuit is one of the biggest legal claims ever filed in a British court.[45] The case, which has been the subject of jurisdictional challenge, was delayed due to the COVID-19 pandemic.[46]
In November 2020, in the High Court sitting in Manchester, the claims were struck out on the grounds that they amounted to an abuse of the process of the court.[47] On 27 July 2021, the Court of Appeal granted the claimants leave to appeal against the November 2020 ruling.[48][49] In July 2022, the Court of Appeal allowed the appeal opening the way for the case to proceed in the English courts.[50][51] In 2023, it was announced that Pogust Goodhead had secured a £450m investment from US-based firm Gramercy Funds Management to help fund the Mariana case and "resolve existing cases successfully".[52]
In March 2023, it was reported that BHP faces an enlarged class-action lawsuit seeking damages of up to U$65 billion for its role in the dam collapse, with the number of claimants more than tripling to 700,000.[53] Approximately 100,000 claimants subsequently exited the claim.[54] Of the remaining 600,000 claimants, 200,000 had already received a total of US$2 billion in compensation through Brazilian proceedings.[55] In April 2024, it was reported that payouts from the court action were to be delayed past the original claimant forecasts, with the case now expected to be completed in 2027.[56] During the trial, it emerged that claims had been filed for oily hair, chickenpox, Alzheimer's disease, and flowers not being as beautiful as before.[57] Lawyers fees in the case are projected to exceed US$680 million.[58] BHP continues to deny the claim in its entirety.[59] In August 2025, BHP Group and Vale had offered US$1.4 billion to settle the case.[60]
On 14 November 2025, High Court judge Finola O'Farrell ruled BHP strictly liable for the disaster. O'Farrell affirmed that "the risk of collapse of the dam was foreseeable", adding: "It is inconceivable that a decision would have been taken to continue raising the height of the dam in those circumstances and the collapse could have been averted".[61] Furthermore, the judge cited serious negligence, as technical warnings were ignored and essential studies were not conducted, allowing the dam to continue being raised even in the face of clear signs of risk. The group stated it intends to appeal over the decision. The amount of compensation to be paid will be determined in another trial, scheduled for October 2026.[62][63] Amid the 2025 United Nations Climate Change Conference held in the Brazilian city of Belém, the Movimento dos Atingidos por Barragens (Movement of People Affected by Dams—MAB) celebrated the decision: "It actually legitimises the struggle. And the fact that the Court finds BHP liable shows that they really have to pay and have to make reparations to those affected."[64]
Government settlement agreement
On 25 October 2024, mining companies BHP and Vale signed an agreement with the Brazilian government to pay nearly US$30 billion in compensation over the Mariana Dam collapse. The terms include $18 billion in funding for public authorities and $5.6 billion in additional compensation, resettlement, and environment restoration. The signing ceremony was attended by Brazilian President Luiz Inacio Lula de Silva.[65]
There is speculation that the agreement could end more than one hundred lawsuits against the mining companies in Brazil, and possibly limit legal action abroad. Vale's vice-president for corporate and external affairs, Alexandre D'Ambrosio, indicated that the compensation deal undermines the foundation of the London case.[66]
On 6 November 2024, the Supreme Federal Court (STF) unanimously validated the agreement reached by the federal government, the states of Minas Gerais, Espírito Santo and mining companies to repair the damage caused by the Mariana dam collapse.[67]
Reactions
National
The city immediately began a campaign to collect donations for the homeless, stressing the urgent need for donations of toothbrushes, towels, glasses, cutlery, disposable dishes and especially drinking water. A special bank account was opened to receive cash donations.[68] All municipal events since the day of the disaster until 16 November were canceled. The note from the Mayor's Office said that "at this point, the city of Mariana is focused on rescue work and support".
The Federal Government, through the Minister's Chief of Staff, Jaques Wagner, put the Federal forces at the disposal of the State of Minas Gerais. The Minister came into contact with the Governor, Fernando Pimentel, to put the Federal forces. Jaques Wagner announced President Dilma Rousseff by accident before loading it back from a trip to Brazil to Brasília.[69]
The Roman Catholic Archdiocese of Mariana said: "We express our most heartfelt sympathy to the families who have had their homes and property destroyed and those who mourn the death of their loved ones, victims of this disaster of incalculable proportions. The point is to unite efforts to minimise the distress and suffering of all those affected by this tragedy. We call upon our communities to provide support to victims. [...]. We pray to God to strengthen and comfort, with your generous love, all who have been affected by this accident". The Diocese of Itabira and Three Lakes and the East Regional II CNBB, comprising the territories of the States of Minas Gerais and Espírito Santo, also issued notes of solidarity with those affected by tragedy.
A football match between Cruzeiro and São Paulo on 8 November in Belo Horizonte hosted a collection of resources to help the victims.[70]
International
A United Nations report shows evidence of the disaster, "50 million tons of iron ore waste, contained high levels of toxic heavy metals and other toxic chemicals in the river Doce".[71] In fact, the scale of the environmental damage is the equivalent of 20,000 Olympic swimming pools of toxic mud waste contaminating the soil, rivers and water system of an area covering over 850 km.[71] The authors stressed that actions taken by the Brazilian government, Vale and BHP Billiton to prevent harm were insufficient.[71] On the other hand, BHP claims that although heavy metals were found, the difference in concentration was found not to differ significantly from that found in the 2010 geologic survey. The company said the tailings that entered the Rio Doce were composed of clay and silt from the processing of earth containing iron ore, which is naturally abundant in the region.[72]
The French spokesman for the Ministry of Foreign Affairs, and Romain Nadal expressed their condolences. A spokesman commented, "We were told with emotion of the disruption of the mining dams in the State of Minas Gerais in the Southeast region."
American band Pearl Jam, who performed in Belo Horizonte on 20 November 2015, promised to donate the proceeds of the concert to victims of the disaster. Singer Eddie Vedder gave a speech calling for harsh punishments to be applied to Samarco and others involved.[73]
See also
- List of non-water floods
- Brumadinho dam disaster – a 2019 tailings dam failure in Brumadinho, Brazil, killing 270 people
External links
- The Mariana mining disaster - A journey through Brazil's worst environmental disaster at france24.com
- Rejeito, documentary by Pedro de Filippis about the fear of more disasters
References
- Lucília Souza Miranda, Antonio Carlos. Hidden impacts of the Samarco mining waste dam collapse to Brazilian marine fauna - an example from the staurozoans (Cnidaria) Biota Neotropica, 2016, retrieved 17 November 2025^
- Dam burst at mining site devastates Brazilian town Al Jazeera, 6 November 2015, retrieved 6 November 2015^
- Brazil dam burst: Six months on, the marks left by sea of sludge BBC News, 5 May 2016^
- Andrew Willis, David Stringer. Dam Owned by Iron-Ore Giants Bursts, Flooding Brazil Valley Bloomberg, 7 November 2015, retrieved 7 November 2015^
- Humberto Trajano. Quase 3 anos após tragédia de Mariana, projeto para novo distrito de Paracatu de Baixo é aprovado G1, Globo Comunicação e Participações S.A., 3 September 2016, retrieved 8 November 2019^
- Brazil dam burst: Six months on, the marks left by sea of sludge BBC News, 5 May 2016^
- Flávio Fonseca do Carmo. Fundão tailings dam failures: the environment tragedy of the largest technological disaster of Brazilian mining in global context Perspectives in Ecology and Conservation, Elsevier, July–September 2017^
- Boechat: Mariana é a maior tragédia ambiental do Brasil TV UOL, 9 November 2015, retrieved 30 November 2015^
- Acidente na barragem de Samarco é "a maior tragédia ambiental" do Brasil Rede Angola, 21 November 2015, retrieved 30 November 2015^
- Sebastião Salgado: 'É a maior tragédia ambiental do Brasil. Mas tem solução' El País, 19 November 2015, retrieved 30 November 2015^
- Ryan Rifai. Toxic sludge reaches Atlantic after Brazil dams burst Al Jazeera, 22 November 2015, retrieved 30 November 2015^
- Anger rises as Brazilian mine disaster threatens river and sea with toxic mud The Guardian, 22 November 2015, retrieved 24 December 2015^
- Mathew Dunckley. BHP Billiton rebuts Samarco dam report The Sydney Morning Herald, 13 November 2015, retrieved 13 November 2015^
- Dom Phillips. Brazil's mining tragedy: was it a preventable disaster? The Guardian, 25 November 2015, retrieved 24 December 2015^
- Dom Phillips, Davilson Brasileiro. Brazil dam disaster: firm knew of potential impact months in advance The Guardian, 1 March 2018, retrieved 2 April 2019^
- Lia Timson. 'Profit before people': documents allege BHP execs were warned over deadly dam Sydney Morning Herald, 4 March 2019, retrieved 2 April 2019^
- STF referenda acordo para reparação de danos causados pela tragédia em Mariana (MG) retrieved 7 November 2024^
- Cássio Cardoso Pereira, Stephannie Fernandes, Geraldo Wilson Fernandes, Fernando Figueiredo Goulart. Eight years after the Fundão tailings dam collapse: chaos on the muddy banks Nature Conservation, 20 August 2024^
- Mine tailings storage: Safety is no accident United Nations, c. 2015, retrieved 30 June 2018^
- Arsenic and mercury found in river days after Brazil dam burst The Guardian, 25 November 2015, retrieved 8 August 2017^
- Samarco mine tragedy: Toxic mud from Brazil mine spill reaches Atlantic Ocean ABC News, Australian Broadcasting Corporation, 22 November 2015, retrieved 30 November 2015^
- Paul Robson. The river is dead - The impact of the catastrophic failure of the Fundão tailings dam London Mining Network, 2017, retrieved 8 November 2019^
- Hédio Júnior. Sinais de lama chegam à Bahia, perto de Abrolhos e Trancoso; Ibama notifica Samarco Estado de Minas, 7 January 2016, retrieved 8 January 2016^
- Parque Nacional Marinho dos Abrolhos Brazilian Ministry of Tourism, retrieved 8 January 2016^
- Vale doou à metade dos deputados da Comissão do Rio Doce. Empresa doou R$388,7 mil para os deputados estaduais da Comissão G1, 9 November 2015^
- Deputados que vão apurar tragédia em Mariana receberam R$ 2,6 mi da Vale noticias.uol.com.br^
- Paul Kiernan. Samarco Warned of Problems at Dam, Engineer Says The Wall Street Journal, 17 January 2016, retrieved 22 January 2016^
- Humberto Tostes Ferreira. Modernização Do Direito Penal E Responsabilidade Penal da Pessoa Jurídica: Um Estudo De Casos Dos Crimes da Samarco Mineração S/A Escola da Magistratura Do Estado Do Rio de Janeiro [School of Magistracy of the State of Rio de Janeiro], 2021, retrieved 21 November 2025^
- Home fundaoinvestigation.com, retrieved 5 July 2020^
- Gilson de Farias Neves Jr. Gitirana, João Paulo Tavares Souza, Nícolas Rodrigues Moura. Análise 2D e 3D da Estabilidade da Barragem de Fundão Revista Eletrônica de Engenharia Civil, 12 May 2020^
- Brazil mining company Samarco suspended over dams burst bbc.com, BBC News, 9 November 2015, retrieved 11 November 2015^
- Vale and BHP fined for deadly Brazilian dam burst bbc.com, BBC News, 13 November 2015, retrieved 13 November 2015^
- Eine schlammbraun gewordene Lebensader 27 November 2015, retrieved 30 November 2015^
- Samarco, Brazil move closer on $4.8B dam-disaster settlement CNBC, 22 January 2016, retrieved 22 January 2016^
- BHP Billiton's Samarco costs top US$3 billion abc.net.au, ABC News, 28 July 2016, retrieved 7 November 2018^
- Maryam Safari, Vincent Bicudo de Castro, Ileana Steccolini. The interplay between home and host logics of accountability in multinational corporations (MNCs): the case of the Fundão dam disaster Accounting, Auditing & Accountability Journal, 9 June 2020^
- Thuy Ong. BHP-owned Samarco agrees to pay Brazil Government $3.2 billion for dam collapse abc.net.au, ABC News, 2 March 2016, retrieved 7 November 2018^
- Samarco staff and BHP executives charged with homicide over Brazil dam spill abc.net.au, ABC News, 21 October 2016, retrieved 7 November 2018^
- Kenneth Rapoza. 'Worst Company In The World' Award Goes To... Forbes, 30 January 2012, retrieved 30 November 2015^
- BHP signs deal to suspend $55b Samarco lawsuit for two years abc.net.au, ABC News, 26 June 2018, retrieved 7 November 2018^
- BHP to settle US Samarco class action for $US50m Australian Mining, 9 August 2018, retrieved 7 November 2018^
- BHP says Brazil court approves Samarco settlement Reuters, retrieved 7 November 2018^
- Sarah Danckert. BHP class action heats up as 30,000 shareholders sign up The Sydney Morning Herald, 30 October 2018, retrieved 7 November 2018^
- Kirstin Ridley, Barbara Lewis. BHP faces $5 billion claim over 2015 Brazil dam failure Reuters, 7 May 2019, retrieved 3 May 2020^
- Alex Gluyas. BHP slapped with record lawsuit over Brazil dam collapse Australian Mining, 8 May 2019, retrieved 8 November 2019^
- Muncipio De Mariana & Ors v BHP Group Plc [2020] EWHC 928 (TCC) bailii.org, 20 April 2020^
- Muncipio De Mariana & Ors v BHP Group Plc [2020] EWHC 2930 (TCC) bailii.org, 9 November 2020^
- Edward Thicknesse. Court of Appeal reopens landmark £5bn lawsuit against BHP for Brazil dam collapse City A.M., 27 July 2021^
- Kirstin Ridley. London judges reverse course to reopen $7 bln Brazil dam lawsuit against BHP Reuters, 27 July 2021^
- Phoebe Weston. Victims of Brazil's worst environmental disaster to get day in UK courts The Guardian, 8 July 2022^
- Municipio De Mariana & Ors v BHP Group (UK) Ltd & Anor [2022] EWCA Civ 951 England and Wales Court of Appeal (Civil Division), 8 July 2022, retrieved 10 October 2022^
- Gramercy to generate $90m annually from 2023 Pogust Goodhead deal Hedgeweek.com, 23 May 2024, retrieved 10 October 2024^
- BHP faces $65 billion damages claim over Brazil mine disaster The Sydney Morning Herald, 24 October 2024, retrieved 13 September 2024^
- BHP accuses class action law firm of 'losing' 100,000 claimants Australian Financial Review, 30 June 2024, retrieved 13 September 2024^
- Eve Erskine. Revealed: The cases to watch in October The Lawyer, 30 September 2024, retrieved 2 October 2024^
- Ação sobre vítimas de Mariana só será concluída em 2027 Poder360, 23 April 2024, retrieved 13 September 2024^
- Chickenpox and faded flowers: BHP challenges size of $70b lawsuit Australian Financial Review, 24 October 2024, retrieved 1 November 2024^
- Lawyer fees for class action against BHP top $680 million Australian Financial Review, 8 August 2024, retrieved 13 September 2024^
- Update - United Kingdom group action bhp.com, 16 March 2023, retrieved 21 November 2025^
- BHP, Vale offer $1.4 billion settlement in UK lawsuit over Brazil dam disaster, FT reports Reuters, 7 August 2025, retrieved 8 August 2025^
- Brian Melley. London judge finds global mining company BHP Group liable in Brazil's worst environmental disaster Associated Press, 14 November 2025, retrieved 14 November 2025^
- Rafaela Mansur, Rodrigo Salgado. BHP, acionista da Samarco, é condenada pela Justiça inglesa em processo sobre rompimento de barragem em Mariana G1, 14 November 2025, retrieved 14 November 2025^
- Jillian Ambrose. Mining firm BHP found liable in UK for disastrous Brazilian dam collapse The Guardian, 14 November 2025, retrieved 15 November 2025^
- Sayonara Moreno. Movimento de Atingidos comemora condenação da BHP pela justiça inglesa Agência Brasil, 14 November 2025, retrieved 15 November 2025^
- Mining giants sign $30bn settlement for Brazil 2015 dam collapse bbc.co.uk, BBC News, 25 October 2024, retrieved 1 November 2024^
- Lisandra Paraguassu. Brazil seals $30 billion compensation deal with BHP, Vale over 2015 dam collapse Reuters, 25 October 2024, retrieved 1 November 2024^
- STF valida acordo para reparação de danos por rompimento de barragem em Mariana (MG) G1, 6 November 2024, retrieved 7 November 2024^
- Comunicado sobre as doações de donativos prefeitura2014.pmmariana.com.br, Prefeitura Municipal de Mariana, retrieved 13 November 2015^
- Governo garante apoio à cidade mineira de Mariana, inundada por lama após rompimento de barragens Portal Brasil, 9 November 2015, retrieved 21 November 2025^
- Cruzeiro arrecadará doações para vítimas de tragédia em Mariana O Tempo, 6 November 2015, retrieved 30 November 2015^
- Paul Kiernan. Brazil Dam's Failure Flooded Region With Toxic Waste, U.N. Report Says The Wall Street Journal, 25 November 2015, retrieved 27 November 2015^
- Stephen Letts. BHP Billiton denies UN claims Brazil dam disaster mud is 'toxic', damage size of 20,000 Olympic pools abc.net.au, Australian Broadcasting Corporation, 26 November 2015, retrieved 28 September 2017^
- Pearl Jam Calls for Justice in Mariana and Promises to Donate Revenue from Tickets to Victims Folha de S.Paulo, 23 November 2015, retrieved 30 November 2015^